    PracticePMI PMP®PMI PMP Practice Exam 4Question 30
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge transferproject transitionoperations handovercapability building

    PMP · Question 30 · Task 16: Ensure knowledge transfer for project continuity

    A project manager is preparing for a planned transition of a software development project from the development team to the operations team. The operations team has limited experience with the new technology stack and will be responsible for ongoing maintenance and support. The development team has been focused on feature delivery and has not documented many of their architectural decisions and troubleshooting procedures. What should the project manager do FIRST?

    Answer options:

    A.

    Schedule intensive training sessions for the operations team on the new technology stack

    B.

    Extend the development team's involvement to provide ongoing support during the transition

    C.

    Conduct a knowledge transfer assessment to identify critical information gaps and develop a comprehensive transfer plan

    D.

    Create detailed documentation of all system components and procedures

    How to approach this question

    Look for systematic approaches that assess knowledge gaps and develop comprehensive transfer plans based on recipient needs.

    Full Answer

    C.Conduct a knowledge transfer assessment to identify critical information gaps and develop a comprehensive transfer plan✓ Correct
    Effective knowledge transfer requires systematic assessment of existing knowledge, identification of gaps, and understanding of recipient needs to develop comprehensive transfer plans.

    Common mistakes

    Students often choose training or documentation approaches rather than recognizing the need to assess knowledge gaps and transfer requirements first.
    Question 29All questionsQuestion 31

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →