PMP · Question 29 · Task 15: Manage project issues
During project execution, a risk that was identified in the risk register has materialized into an active issue: a key technical resource has left the organization unexpectedly, and their specialized knowledge is critical for the next phase of development. The resource had been identified as a single point of failure, but knowledge transfer was planned for later in the project. What should the project manager do FIRST?
During project execution, a risk that was identified in the risk register has materialized into an active issue: a key technical resource has left the organization unexpectedly, and their specialized knowledge is critical for the next phase of development. The resource had been identified as a single point of failure, but knowledge transfer was planned for later in the project. What should the project manager do FIRST?
Answer options:
Immediately assess the scope of knowledge gap and identify the most critical information needed to continue the project
Contact the departed resource to arrange knowledge transfer sessions
Hire a replacement resource with similar technical expertise
Escalate to senior management to determine how to proceed
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 4
90 questions · hints · full answers · grading
Expert