    PracticePMI PMP®PMI PMP Practice Exam 2Question 49
    Hard1 markMultiple Choice
    Task 10: Build shared understandingcross-functional-teamsalignmentshared-objectivescollaborative-planning

    PMP · Question 49 · Task 10: Build shared understanding

    A project manager is leading a cross-functional team that includes members from engineering, marketing, and operations departments. Each department has different success criteria and priorities for the project. During planning sessions, conflicts arise about feature prioritization and resource allocation. What should the project manager do to align the team?

    Answer options:

    A.

    Make prioritization decisions based on the department with the most project influence

    B.

    Facilitate workshops to identify shared objectives and create unified success criteria

    C.

    Assign each department responsibility for their own priorities and deliverables

    D.

    Escalate the prioritization conflicts to senior management for resolution

    How to approach this question

    Cross-functional conflicts require collaborative approaches that build shared understanding and unified objectives rather than power-based decisions or separation.

    Full Answer

    B.Facilitate workshops to identify shared objectives and create unified success criteria✓ Correct
    Cross-functional team success requires shared understanding and unified objectives. Facilitated workshops help identify common goals and create alignment while respecting different departmental perspectives.

    Common mistakes

    Making power-based decisions, creating departmental silos, or escalating without attempting collaborative resolution.
    Question 48All questionsQuestion 50

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard