    PracticePMI PMP®PMI PMP Practice Exam 2Question 03
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksrisk-managementservant-leadershipagile-methodologyteam-collaboration

    PMP · Question 03 · Task 3: Assess and manage risks

    During iteration planning for a hybrid software project, the team identifies a new technical risk: the third-party API they planned to integrate may not support the required data volume for peak usage periods. This could impact the current sprint goal and the upcoming release to production. The team estimates this affects 40% of the planned sprint work. Which TWO actions should the project manager take FIRST to address this risk?

    Answer options:

    A.

    Add the risk to the product backlog as a high-priority user story for future sprints

    B.

    Work with the team to identify alternative APIs or technical solutions immediately

    C.

    Conduct a spike to assess the API's actual capacity and limitations within the current sprint

    D.

    Remove the integration from the current sprint scope to avoid risk

    E.

    Escalate to the product owner for immediate prioritization decision

    F.

    Document the risk in the risk register and schedule a risk review meeting

    How to approach this question

    Look for immediate, collaborative actions that both assess the risk (spike) and explore solutions (alternative APIs). Avoid premature escalation or scope changes before assessment.

    Full Answer

    In agile environments, risks affecting significant sprint work require immediate collaborative action. Spikes provide data-driven assessment while solution exploration demonstrates servant leadership in removing team blockers.

    Common mistakes

    Choosing documentation or escalation over immediate collaborative problem-solving, or making scope decisions before proper risk assessment.
    Question 02All questionsQuestion 04

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...HardQ06A project manager notices that a highly skilled team member has become withdrawn over the past tw...Hard
    View all 100 questions →