    PracticePMI PMP®PMI PMP Practice Exam 2Question 25
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsmatrix-organizationresource-allocationfunctional-managernegotiation

    PMP · Question 25 · Task 8: Negotiate project agreements

    A project manager is leading a cross-functional team where members report to different functional managers. One team member consistently arrives late to meetings and misses deadlines, citing competing priorities from their functional manager. The functional manager confirms they are giving the team member other high-priority work. What should the project manager do?

    Answer options:

    A.

    Escalate to senior management to resolve the resource conflict

    B.

    Replace the team member with someone who has more availability

    C.

    Document the team member's poor performance for their functional manager

    D.

    Negotiate with the functional manager to establish clear priorities and time allocation for the team member

    How to approach this question

    In matrix organizations, resource conflicts require negotiation between project and functional managers to establish clear priorities and allocations.

    Full Answer

    D.Negotiate with the functional manager to establish clear priorities and time allocation for the team member✓ Correct
    Matrix organizations require clear agreements between project and functional managers about resource allocation and priorities. Negotiation addresses the root cause of competing demands on team members.

    Common mistakes

    Treating this as a performance issue, escalating without attempting negotiation, or trying to replace the team member without addressing the underlying conflict.
    Question 24All questionsQuestion 26

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →