    PracticePMI PMP®PMI PMP Practice Exam 2Question 17
    Hard1 markMultiple Choice
    Task 3: Support team performanceteam-performanceservant-leadershipperformance-improvementcoaching

    PMP · Question 17 · Task 3: Support team performance

    A team member consistently delivers high-quality work but struggles with time management and frequently misses deadlines. This affects other team members who depend on their deliverables. The team member is aware of the issue and wants to improve. What should the project manager do to support this team member's performance?

    Answer options:

    A.

    Assign shorter tasks to the team member to reduce the impact of delays

    B.

    Pair the team member with someone who has strong time management skills

    C.

    Work with the team member to identify specific time management challenges and develop improvement strategies

    D.

    Document the performance issue and establish formal deadlines with consequences

    How to approach this question

    Look for developmental approaches that help the team member improve their capabilities rather than working around the problem or being punitive.

    Full Answer

    C.Work with the team member to identify specific time management challenges and develop improvement strategies✓ Correct
    Servant leadership focuses on developing team members' capabilities. Working collaboratively to identify specific challenges and develop strategies addresses the root cause while supporting the individual's growth.

    Common mistakes

    Working around the problem instead of addressing it, using punitive approaches, or not leveraging the team member's motivation to improve.
    Question 16All questionsQuestion 18

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →