Hard1 markShort Answer
Task 6: Plan and manage scheduleProcessScheduleCalculation

PMP · Question 018 · Task 6: Plan and manage schedule

A project has the following activity duration estimates: Activity A (Optimistic: 3, Most Likely: 5, Pessimistic: 13). Using the Beta (PERT) distribution, what is the expected duration for Activity A? (Enter the number only).

How to approach this question

Use the PERT formula: (O + 4M + P) / 6.

Full Answer

(3 + 4*5 + 13) / 6 = (3 + 20 + 13) / 6 = 36 / 6 = 6.

Common mistakes

Using the triangular distribution (O+M+P)/3.