Hard1 markMultiple Choice
PMP · Question 015 · Task 16: Ensure knowledge transfer
A project manager takes over a project in execution. The project is using a predictive approach. The PM notices that the Lessons Learned Register is empty. What should the PM do?
A project manager takes over a project in execution. The project is using a predictive approach. The PM notices that the Lessons Learned Register is empty. What should the PM do?
Answer options:
A.
Wait until the project closure phase to populate the register.
B.
Schedule a meeting with the team to identify lessons learned to date and update the register.
C.
Fill out the register based on the previous project manager's emails.
D.
Ignore the register as the project is already halfway through.
How to approach this question
Lessons Learned is a continuous process, not a one-time event.
Full Answer
B.Schedule a meeting with the team to identify lessons learned to date and update the register.✓ Correct
Task 16 (Knowledge Transfer) and Task 12 (Manage Artifacts). The PM must ensure knowledge is captured continuously to improve current performance.
Common mistakes
Choosing A (Old school thinking that lessons learned is a closing activity).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert