Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesProcessCost ManagementCalculation

PMP · Question 007 · Task 5: Plan and manage budget and resources

A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000 and the Earned Value (EV) is $40,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols).

How to approach this question

Calculate CPI first, then use the formula EAC = BAC / CPI.

Full Answer

1. Calculate CPI: EV ($40,000) / AC ($45,000) = 0.8888...<br/>2. Calculate EAC: BAC ($100,000) / CPI (0.8888...) = $112,500.<br/>Alternatively: $100,000 * ($45,000 / $40,000) = $112,500.

Common mistakes

Using the wrong EAC formula (e.g., AC + BAC - EV) which applies when variance is atypical.

Practice the full PMI PMP Mini Practice Exam

20 questions · hints · full answers · grading

More questions from this exam