Hard1 markShort Answer
PMP · Question 007 · Task 5: Plan and manage budget and resources
A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000 and the Earned Value (EV) is $40,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols).
A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. The Actual Cost (AC) is $45,000 and the Earned Value (EV) is $40,000. The project manager expects the current cost variance to be typical for the remainder of the project. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols).
How to approach this question
Calculate CPI first, then use the formula EAC = BAC / CPI.
Full Answer
1. Calculate CPI: EV ($40,000) / AC ($45,000) = 0.8888...<br/>2. Calculate EAC: BAC ($100,000) / CPI (0.8888...) = $112,500.<br/>Alternatively: $100,000 * ($45,000 / $40,000) = $112,500.
Common mistakes
Using the wrong EAC formula (e.g., AC + BAC - EV) which applies when variance is atypical.
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert