Hard1 markMultiple Choice
PMP · Question 19 · Task 1: Plan and manage project compliance
A project manager discovers that a team member has been saving project documents to their personal cloud storage drive to work from home, violating company security policies. What should the project manager do FIRST?
A project manager discovers that a team member has been saving project documents to their personal cloud storage drive to work from home, violating company security policies. What should the project manager do FIRST?
Answer options:
A.
Report the security breach to the IT security department immediately.
B.
Privately discuss the security violation with the team member and require immediate removal of the files.
C.
Fire the team member for cause.
D.
Update the project risk register.
How to approach this question
Safety/Compliance first, but done via direct management. Stop the bleeding.
Full Answer
B.Privately discuss the security violation with the team member and require immediate removal of the files.✓ Correct
Compliance (Task 1) requires adherence to rules. The PM must stop the violation immediately (remove files) and educate the member. Reporting to IT (A) follows, but securing the data is step 1.
Common mistakes
Just documenting it (D) or escalating without securing the data (A).
Practice the full PMI PMP Mini Practice Exam 2
20 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
Expert