PMP · Question 05 · Task 8: Negotiate project agreements
During a negotiation with a vendor for a critical component, the vendor states they cannot meet the required delivery date due to supply chain issues. This component is on the critical path. The vendor offers a 10% discount if the deadline is extended by two weeks. What is the BEST course of action for the project manager?
Answer options:
Accept the discount and update the schedule baseline immediately.
Demand the vendor meet the original date or face penalties.
Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.
Look for an alternative vendor who can meet the date.