For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 05
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsPeopleNegotiationProcessSchedule

    PMP · Question 05 · Task 8: Negotiate project agreements

    During a negotiation with a vendor for a critical component, the vendor states they cannot meet the required delivery date due to supply chain issues. This component is on the critical path. The vendor offers a 10% discount if the deadline is extended by two weeks. What is the BEST course of action for the project manager?

    Answer options:

    A.

    Accept the discount and update the schedule baseline immediately.

    B.

    Demand the vendor meet the original date or face penalties.

    C.

    Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.

    D.

    Look for an alternative vendor who can meet the date.

    How to approach this question

    Always 'Analyze' or 'Assess' before acting. Never accept a change to the critical path without understanding the impact.

    Full Answer

    C.Analyze the impact of the two-week delay on the project schedule and cost baseline before responding.✓ Correct
    A delay on the critical path extends the project end date. The PM must calculate if the 10% discount covers the cost of project delay (e.g., penalties, lost revenue).

    Common mistakes

    Assuming the discount is worth it or immediately fighting the vendor without data.
    Question 04All questionsQuestion 06

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ06A project has a Budget at Completion (BAC) of $100,000. The project is currently 40% complete. Th...Hard
    View all 20 questions →