    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 10
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodology/methods and practicesProcessMethodologyHybrid

    PMP · Question 10 · Task 13: Determine appropriate project methodology/methods and practices

    Which of the following scenarios BEST describes when a 'Hybrid' project management approach should be selected?

    Answer options:

    A.

    A project with clearly defined requirements, a stable scope, and a team familiar with the technology.

    B.

    A research and development project where the final outcome is unknown and discovery is the primary goal.

    C.

    A project with fixed regulatory requirements for the final deliverable but uncertain user interface preferences.

    D.

    A short-term project with a single deliverable and no expected changes.

    How to approach this question

    Look for a mix of characteristics: some parts stable/fixed (Predictive) and some parts evolving/uncertain (Agile).

    Full Answer

    C.A project with fixed regulatory requirements for the final deliverable but uncertain user interface preferences.✓ Correct
    Hybrid approaches are ideal when different deliverables within the same project require different lifecycle management (e.g., construction vs. software).

    Common mistakes

    Selecting Agile for everything just because it's popular.
    Question 09All questionsQuestion 11

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard