For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice Exam 2Question 08
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valueProcessAgileRetrospective

    PMP · Question 08 · Task 1: Execute project with the urgency required to deliver business value

    An agile team is struggling with 'Carryover'—user stories are frequently not completed within the sprint and spill over to the next. This is affecting the predictability of the release. What is the MOST effective action the project manager (acting as Scrum Master) can take?

    Answer options:

    A.

    Extend the sprint duration to allow the team to finish the work.

    B.

    Assign the unfinished stories to the most senior developer to complete quickly.

    C.

    Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.

    D.

    Increase the team's capacity by adding more resources.

    How to approach this question

    Identify the process improvement mechanism in Agile (Retrospective) and the likely artifacts involved (Definition of Ready).

    Full Answer

    C.Facilitate a retrospective focused on root cause analysis of the carryover and adjust the Definition of Ready or velocity.✓ Correct
    Carryover usually indicates stories are too large or not well-defined. The Retrospective is the venue to analyze this, and the Definition of Ready is the control mechanism.

    Common mistakes

    Trying to 'manage' the problem by changing time (sprint length) or resources rather than fixing the process.
    Question 07All questionsQuestion 09

    Practice the full PMI PMP Mini Practice Exam 2

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager has taken over a project where the team morale is low. Team members feel their ...HardQ03A high-performing team member in an agile project requests to attend a specialized training cours...HardQ04A project manager is leading a virtual team spread across four different time zones. Communicatio...HardQ05During a negotiation with a vendor for a critical component, the vendor states they cannot meet t...Hard
    View all 20 questions →