PMP · Question 58 · Task 17: Plan and manage project/phase closure or transitions
A project has been terminated early due to budget cuts. What should the project manager do FIRST?
Answer options:
Release the team immediately to save money.
Follow the formal project closure procedures.
Delete all project files.
Write a final report blaming the finance department.
60 questions · hints · full answers · grading