A project manager is tailoring the project processes for a small, low-risk internal project. Which actions are appropriate? (Select TWO)
Answer options:
Skip the project charter to save time.
Combine the Scope, Schedule, and Cost plans into a simplified Project Management Plan.
Eliminate risk management entirely.
Bypass the lessons learned process.
Use a lightweight change control process with the sponsor as the sole approver.
Remove the requirement for a Work Breakdown Structure.