PMP · Question 40 · Task 11: Plan and manage procurement
An agile project needs to outsource a specific component. The team wants to collaborate closely with the vendor, sharing risks and rewards. Which contract structure supports this?
Answer options:
Standard Fixed Price
Dynamic (Agile) Contract with optional scope clauses
Purchase Order
Cost Plus Percentage of Cost