PMP · Question 38 · Task 10: Manage project changes
A project manager receives a change request. Before approving or rejecting it, what must be done?
Answer options:
Update the project schedule.
Analyze the impact on scope, schedule, cost, quality, and risk.
Consult the project sponsor.
Implement a prototype.