PMP · Question 33 · Task 9: Integrate project planning activities
A project manager reviews the following data: CPI = 0.8, SPI = 1.2. What does this indicate about the project status?
Answer options:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Under budget and behind schedule