PMP · Question 30 · Task 8: Plan and manage scope
Which of the following represents the lowest level of the Work Breakdown Structure (WBS)?
Which of the following represents the lowest level of the Work Breakdown Structure (WBS)?
Answer options:
A.
Activity
B.
Control Account
C.
Work Package
D.
Task
How to approach this question
Recall the hierarchy: WBS -> Work Package -> Activities (Schedule).
Full Answer
C.Work Package✓ Correct
The WBS decomposes scope down to the Work Package level. The Work Package is then further decomposed into Activities for the schedule, but Activities are NOT part of the WBS itself.
Common mistakes
Selecting Activity. The WBS is scope-oriented; Activities are time-oriented.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert