Hard1 markMultiple Choice

PMP · Question 30 · Task 8: Plan and manage scope

Which of the following represents the lowest level of the Work Breakdown Structure (WBS)?

Answer options:

A.

Activity

B.

Control Account

C.

Work Package

D.

Task

How to approach this question

Recall the hierarchy: WBS -> Work Package -> Activities (Schedule).

Full Answer

C.Work Package✓ Correct
The WBS decomposes scope down to the Work Package level. The Work Package is then further decomposed into Activities for the schedule, but Activities are NOT part of the WBS itself.

Common mistakes

Selecting Activity. The WBS is scope-oriented; Activities are time-oriented.

Practice the full PMP Process Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam