Hard1 markMultiple Choice
Task 6: Plan and manage scheduleTask 6ScheduleTechniques

PMP · Question 23 · Task 6: Plan and manage schedule

A project is delayed. The project manager needs to compress the schedule without changing the scope. Which two techniques can be used? (Select TWO)

Answer options:

A.

Crashing

B.

Resource Leveling

C.

Fast Tracking

D.

Value Engineering

E.

Monte Carlo Analysis

F.

De-scoping

How to approach this question

Identify the two standard schedule compression techniques defined in PMBOK.

Full Answer

Crashing and Fast Tracking are the two primary methods to shorten a schedule without cutting scope.

Common mistakes

Selecting Resource Leveling (which usually delays the project).