Hard1 markMultiple Choice
PMP · Question 23 · Task 6: Plan and manage schedule
A project is delayed. The project manager needs to compress the schedule without changing the scope. Which two techniques can be used? (Select TWO)
A project is delayed. The project manager needs to compress the schedule without changing the scope. Which two techniques can be used? (Select TWO)
Answer options:
A.
Crashing
B.
Resource Leveling
C.
Fast Tracking
D.
Value Engineering
E.
Monte Carlo Analysis
F.
De-scoping
How to approach this question
Identify the two standard schedule compression techniques defined in PMBOK.
Full Answer
Crashing and Fast Tracking are the two primary methods to shorten a schedule without cutting scope.
Common mistakes
Selecting Resource Leveling (which usually delays the project).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert