PMP · Question 21 · Task 6: Plan and manage schedule
A project is behind schedule. The Critical Path is A-C-E (20 days). Path B-D-E is 18 days. The project manager decides to crash Activity C by 3 days. What is the new project duration?
Answer options:
17 days
18 days
20 days
15 days