For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 21
    Hard1 markMultiple Choice
    Task 6: Plan and manage scheduleTask 6ScheduleCritical Path

    PMP · Question 21 · Task 6: Plan and manage schedule

    A project is behind schedule. The Critical Path is A-C-E (20 days). Path B-D-E is 18 days. The project manager decides to crash Activity C by 3 days. What is the new project duration?

    Answer options:

    A.

    17 days

    B.

    18 days

    C.

    20 days

    D.

    15 days

    How to approach this question

    Check if the critical path shifts. Reduce the crashed path, then compare all paths to find the new longest path.

    Full Answer

    B.18 days✓ Correct
    Task 6 involves modifying the schedule. Crashing reduces the duration of one path, but the project duration is determined by the *longest* path. Path 2 (18 days) prevents the project from finishing in 17 days.

    Common mistakes

    Ignoring the secondary path and assuming the project shortens by the full crash amount.
    Question 20All questionsQuestion 22

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →