PMP · Question 12 · Task 4: Engage stakeholders
A key stakeholder is consistently absent from sprint reviews and complains that the product is not meeting their needs. The project manager has sent email reminders, but the behavior continues. What should the project manager do?
Answer options:
Escalate the issue to the project sponsor immediately.
Continue sending reminders and document the lack of attendance.
Schedule a one-on-one meeting to understand their concerns and barriers to attendance.
Ask the Product Owner to represent the stakeholder's interests.
60 questions · hints · full answers · grading