PMP · Question 08 · Task 3: Assess and manage risks
A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?
Answer options:
Avoid
Mitigate
Transfer
Accept
60 questions · hints · full answers · grading