For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 08
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksTask 3RiskMatching Conversion

    PMP · Question 08 · Task 3: Assess and manage risks

    A project manager identifies a risk that a critical vendor might go bankrupt. The project team decides to contract with a secondary vendor to be on standby for a retainer fee. Which risk response strategy is this?

    Answer options:

    A.

    Avoid

    B.

    Mitigate

    C.

    Transfer

    D.

    Accept

    How to approach this question

    Ask: Did we eliminate it (Avoid)? Did we pass it to someone else (Transfer)? Did we reduce prob/impact (Mitigate)? Or did we just wait (Accept)?

    Full Answer

    B.Mitigate✓ Correct
    This is mitigation because the action (hiring a standby) reduces the impact of the risk event. It is not transfer because the project still owns the problem of getting the work done.

    Common mistakes

    Confusing Transfer (insurance/warranties) with Mitigation (reducing impact via redundancy).
    Question 07All questionsQuestion 09

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →