    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTraining

    PMP · Question 98 · Task 1: Plan and manage project compliance

    A project manager is leading a project to develop a new medical device. The project is subject to FDA regulations. The PM wants to ensure that the project team is aware of the compliance requirements. What should the PM do?

    Answer options:

    A.

    Email the regulations to the team.

    B.

    Include compliance training in the project plan and discuss requirements during the kickoff and regular meetings.

    C.

    Assume the team knows the rules since they are experts.

    D.

    Hire a compliance officer to do the work.

    How to approach this question

    Compliance = Training + Communication.

    Full Answer

    B.Include compliance training in the project plan and discuss requirements during the kickoff and regular meetings.✓ Correct
    Task 1 (Compliance) and Task 5 (Training). Compliance is a team sport. The PM ensures the team has the knowledge to be compliant.

    Common mistakes

    Assuming experts know all the specific regulations for this project.
    Question 97All questionsQuestion 99

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →