Medium1 markMultiple Choice

PMP · Question 86 · Task 6: Plan and manage schedule

A project manager is leading a project to build a new stadium. The project is using a predictive lifecycle. The steel beams are delayed by 4 weeks due to a strike. This activity is on the critical path. What is the impact on the project finish date?

Answer options:

A.

No impact if there is float.

B.

The project will be delayed by 4 weeks unless corrective action (crashing/fast-tracking) is taken.

C.

The project will be delayed by 2 weeks.

D.

The PM can use the management reserve to fix the time.

How to approach this question

Critical Path = Zero Float. Delay = Delay.

Full Answer

B.The project will be delayed by 4 weeks unless corrective action (crashing/fast-tracking) is taken.✓ Correct
Task 6 (Schedule). Understanding Critical Path Method (CPM) is essential. Any delay on the CP delays the finish date directly.

Common mistakes

Thinking there is float on the critical path.