Medium1 markMultiple Choice
PMP · Question 86 · Task 6: Plan and manage schedule
A project manager is leading a project to build a new stadium. The project is using a predictive lifecycle. The steel beams are delayed by 4 weeks due to a strike. This activity is on the critical path. What is the impact on the project finish date?
A project manager is leading a project to build a new stadium. The project is using a predictive lifecycle. The steel beams are delayed by 4 weeks due to a strike. This activity is on the critical path. What is the impact on the project finish date?
Answer options:
A.
No impact if there is float.
B.
The project will be delayed by 4 weeks unless corrective action (crashing/fast-tracking) is taken.
C.
The project will be delayed by 2 weeks.
D.
The PM can use the management reserve to fix the time.
How to approach this question
Critical Path = Zero Float. Delay = Delay.
Full Answer
B.The project will be delayed by 4 weeks unless corrective action (crashing/fast-tracking) is taken.✓ Correct
Task 6 (Schedule). Understanding Critical Path Method (CPM) is essential. Any delay on the CP delays the finish date directly.
Common mistakes
Thinking there is float on the critical path.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert