    PracticePMI PMP®PMI PMP Practice ExamQuestion 76
    Medium1 markMultiple Choice
    Task 7: Address and remove impedimentsPeopleServant Leadership

    PMP · Question 76 · Task 7: Address and remove impediments

    A project manager is leading a team that is constantly interrupted by operational requests from other departments. The team's velocity is suffering. What should the PM do?

    Answer options:

    A.

    Tell the team to work harder.

    B.

    Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.

    C.

    Allow the interruptions as they are important to the company.

    D.

    Move the team to a secret location.

    How to approach this question

    Servant Leader = Shield.

    Full Answer

    B.Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.✓ Correct
    Task 7 (Impediments). Interruptions are impediments. The PM protects the team's focus.

    Common mistakes

    Letting the team handle the noise.
    Question 75All questionsQuestion 77

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard