PMP · Question 76 · Task 7: Address and remove impediments
A project manager is leading a team that is constantly interrupted by operational requests from other departments. The team's velocity is suffering. What should the PM do?
Answer options:
Tell the team to work harder.
Act as a shield for the team, intercepting requests and negotiating their priority or deferring them.
Allow the interruptions as they are important to the company.
Move the team to a secret location.