    PracticePMI PMP®PMI PMP Practice ExamQuestion 62
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersPeopleStakeholdersInfluence

    PMP · Question 62 · Task 9: Collaborate with stakeholders

    A project manager is dealing with a difficult stakeholder who constantly criticizes the project in public meetings. The PM decides to meet with the stakeholder privately to ask for their advice on how to improve the project. Which strategy is the PM using?

    Answer options:

    A.

    Avoidance

    B.

    Influence / Engagement (Turning a critic into a supporter).

    C.

    Coercion

    D.

    Escalation

    How to approach this question

    Stakeholder Strategy. Critic -> Advisor.

    Full Answer

    B.Influence / Engagement (Turning a critic into a supporter).✓ Correct
    Task 9 (Collaborate). Engaging a negative stakeholder by giving them a voice (constructively) is a powerful influence strategy.

    Common mistakes

    Thinking you should ignore or fight critics.
    Question 61All questionsQuestion 63

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard