PMP · Question 62 · Task 9: Collaborate with stakeholders
A project manager is dealing with a difficult stakeholder who constantly criticizes the project in public meetings. The PM decides to meet with the stakeholder privately to ask for their advice on how to improve the project. Which strategy is the PM using?
Answer options:
Avoidance
Influence / Engagement (Turning a critic into a supporter).
Coercion
Escalation