PMP · Question 60 · Task 1: Plan and manage project compliance
A project manager is leading a project to build a bridge. The project uses a predictive lifecycle. During excavation, the team finds archaeological artifacts. Work must stop. What is the PM's FIRST action?
Answer options:
Update the schedule.
Secure the site and notify the appropriate authorities/stakeholders as per the compliance plan.
Move the bridge location.
Ignore it and keep digging.