    PracticePMI PMP®PMI PMP Practice ExamQuestion 60
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentCompliance

    PMP · Question 60 · Task 1: Plan and manage project compliance

    A project manager is leading a project to build a bridge. The project uses a predictive lifecycle. During excavation, the team finds archaeological artifacts. Work must stop. What is the PM's FIRST action?

    Answer options:

    A.

    Update the schedule.

    B.

    Secure the site and notify the appropriate authorities/stakeholders as per the compliance plan.

    C.

    Move the bridge location.

    D.

    Ignore it and keep digging.

    How to approach this question

    Compliance Event -> Stop -> Notify.

    Full Answer

    B.Secure the site and notify the appropriate authorities/stakeholders as per the compliance plan.✓ Correct
    Task 1 (Compliance). Regulatory/Legal issues require immediate adherence to the compliance plan.

    Common mistakes

    Thinking about schedule (A) before legality.
    Question 59All questionsQuestion 61

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →