PMP · Question 46 · Task 3: Assess and manage risks
A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?
Answer options:
Use the backup supplier immediately and accept the cost overrun.
Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.
Look for a third supplier.
Cancel the project.
114 questions · hints · full answers · grading