For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 46
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksProcessRiskBudget

    PMP · Question 46 · Task 3: Assess and manage risks

    A project manager is using a predictive methodology. During the execution phase, a major supplier goes bankrupt. This risk was identified in the risk register, and the response plan was to use a backup supplier. However, the backup supplier is now charging double the original price. What should the PM do?

    Answer options:

    A.

    Use the backup supplier immediately and accept the cost overrun.

    B.

    Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.

    C.

    Look for a third supplier.

    D.

    Cancel the project.

    How to approach this question

    Risk happened -> Cost increased -> Change Control for Money.

    Full Answer

    B.Submit a change request to use the contingency reserve (or management reserve if costs exceed contingency) to cover the price difference.✓ Correct
    Task 3 (Risk) and Task 5 (Budget). Executing a risk response that costs more than expected requires budget management (Change Request).

    Common mistakes

    Spending money you don't have (A) without approval.
    Question 45All questionsQuestion 47

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →