PMP · Question 32 · Task 15: Manage project issues
A project manager is reviewing the risk register and notices a risk with a high probability and high impact: 'Vendor delay'. The response plan is 'Mitigate'. However, the vendor has just announced a strike, making the delay 100% certain. What should the project manager do?
Answer options:
Leave it in the risk register and monitor it.
Convert the risk to an issue, execute the contingency plan (if any), and update the issue log.
Perform a qualitative risk analysis again.
Fire the vendor immediately.
114 questions · hints · full answers · grading