For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 113
    Medium1 markMultiple Choice
    Task 5: Plan and manage budget and resourcesProcessBudgetRisk

    PMP · Question 113 · Task 5: Plan and manage budget and resources

    A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Reserve Analysis'. What is this?

    Answer options:

    A.

    Checking the bank account.

    B.

    Comparing the remaining reserves (Contingency) to the remaining risks to see if the funds are adequate.

    C.

    Asking for more money.

    D.

    Spending the money.

    How to approach this question

    Reserve = Risk Money. Analysis = Is it enough?

    Full Answer

    B.Comparing the remaining reserves (Contingency) to the remaining risks to see if the funds are adequate.✓ Correct
    Task 5 (Budget) and Task 3 (Risk). Reserves are tied to risks. As risks expire, reserves can be released. As new risks appear, reserves may need increasing.

    Common mistakes

    Thinking reserves are just 'extra money' for anything.
    Question 112All questionsQuestion 114

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →