PMP · Question 113 · Task 5: Plan and manage budget and resources
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Reserve Analysis'. What is this?
Answer options:
Checking the bank account.
Comparing the remaining reserves (Contingency) to the remaining risks to see if the funds are adequate.
Asking for more money.
Spending the money.
114 questions · hints · full answers · grading