Medium1 markMultiple Choice
PMP · Question 111 · Task 6: Plan and manage schedule
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Crashing'. What is this?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Crashing'. What is this?
Answer options:
A.
Adding resources to critical path activities to shorten the duration.
B.
Performing activities in parallel.
C.
Reducing scope.
D.
Ignoring the schedule.
How to approach this question
Crashing = Money/Resources.
Full Answer
A.Adding resources to critical path activities to shorten the duration.✓ Correct
Task 6 (Schedule). Crashing increases cost to save time.
Common mistakes
Confusing with Fast Tracking.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert