Medium1 markMultiple Choice

PMP · Question 111 · Task 6: Plan and manage schedule

A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM uses 'Crashing'. What is this?

Answer options:

A.

Adding resources to critical path activities to shorten the duration.

B.

Performing activities in parallel.

C.

Reducing scope.

D.

Ignoring the schedule.

How to approach this question

Crashing = Money/Resources.

Full Answer

A.Adding resources to critical path activities to shorten the duration.✓ Correct
Task 6 (Schedule). Crashing increases cost to save time.

Common mistakes

Confusing with Fast Tracking.