For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 33
    Hard1 markMultiple Choice
    Task 17: Plan and manage project/phase closure or transitionsproject closureclosure checklistsystematic closureproject completion

    PMP · Question 33 · Task 17: Plan and manage project/phase closure or transitions

    A project is approaching completion, and the project manager is preparing for project closure. The deliverables have been accepted by the customer, but there are still some outstanding vendor invoices, team members need to be released to other projects, and lessons learned need to be captured. The sponsor is eager to officially close the project. What should the project manager do FIRST?

    Answer options:

    A.

    Develop a closure checklist to ensure all closure activities are completed systematically

    B.

    Release team members to other projects since the deliverables have been accepted

    C.

    Focus on resolving the outstanding vendor invoices to close the financial aspects

    D.

    Proceed with official project closure since the customer has accepted the deliverables

    How to approach this question

    Project closure requires systematic completion of all closure activities. Develop a comprehensive approach before executing individual closure tasks.

    Full Answer

    A.Develop a closure checklist to ensure all closure activities are completed systematically✓ Correct
    Effective project closure requires systematic completion of all closure activities including financial, administrative, resource, and knowledge management tasks. A closure checklist ensures nothing is missed.

    Common mistakes

    Students often choose immediate action on specific closure activities (B or C) or premature official closure (D), missing the need for systematic closure planning.
    Question 32All questionsQuestion 34

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →