For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 13
    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementscontract negotiationvendor managementrisk sharingcollaborative negotiation

    PMP · Question 13 · Task 8: Negotiate project agreements

    A project manager is negotiating a contract with a vendor for critical project components. The vendor is pushing for a fixed-price contract with minimal change provisions, while the project sponsor wants maximum flexibility for potential scope changes. The vendor argues that flexibility increases their risk and cost. What negotiation strategy should the project manager pursue FIRST?

    Answer options:

    A.

    Accept the vendor's fixed-price proposal to ensure cost certainty for the project

    B.

    Insist on a time-and-materials contract to provide maximum flexibility for changes

    C.

    Explore hybrid contract structures that balance cost predictability with change flexibility

    D.

    Escalate the contract decision to the sponsor and let them negotiate directly with the vendor

    How to approach this question

    Look for collaborative negotiation strategies that address both parties' underlying interests rather than positional demands.

    Full Answer

    C.Explore hybrid contract structures that balance cost predictability with change flexibility✓ Correct
    Effective negotiation focuses on underlying interests rather than positions. Hybrid contract structures can provide cost predictability while allowing for managed flexibility through structured change processes.

    Common mistakes

    Students often choose one party's position (A or B) or avoid responsibility through escalation (D), missing the opportunity for collaborative problem-solving.
    Question 12All questionsQuestion 14

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →