    PracticePMI PMP®PMI PMP Practice Exam 5Question 06
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceregulatory compliancerisk managementpharmaceutical projectsFDA regulations

    PMP · Question 06 · Task 1: Plan and manage project compliance

    A pharmaceutical project must comply with FDA regulations. During a routine audit preparation, the project manager discovers that a team member unknowingly used a non-compliant data storage method for clinical trial information over the past month. The data integrity appears intact, but the storage method violates regulatory requirements. What should the project manager do FIRST?

    Answer options:

    A.

    Document the issue in the risk register and implement additional training for all team members

    B.

    Immediately halt the affected work and assess the full compliance impact with the regulatory team

    C.

    Report the team member to HR for not following established procedures

    D.

    Continue the work while implementing the correct storage method going forward

    How to approach this question

    In compliance scenarios, prioritize immediate containment and assessment over documentation, training, or blame. Regulatory violations require urgent response.

    Full Answer

    B.Immediately halt the affected work and assess the full compliance impact with the regulatory team✓ Correct
    Regulatory compliance violations require immediate containment to prevent further violations and comprehensive impact assessment to determine corrective actions and potential reporting requirements.

    Common mistakes

    Students often choose documentation (A) or continuing work (D), underestimating the severity and urgency required for compliance violations in regulated industries.
    Question 05All questionsQuestion 07

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard