Hard1 markMultiple Choice
Task 1: Execute project with the urgency required to deliver business valueproject executionteam burnoutsustainable capacityvalue delivery

PMP · Question 87 · Task 1: Execute project with the urgency required to deliver business value

A mobile application development project is approaching a critical client deadline, but the team is showing signs of severe burnout from working extended hours for the past six weeks. Code quality issues are increasing, team communication is becoming strained, and three developers have requested time off. The client has indicated that missing the deadline could result in contract cancellation and significant financial penalties. What should the project manager do FIRST?

Answer options:

A.

Assess the team's current sustainable capacity and work with the client to identify the core features that deliver maximum business value

B.

Negotiate with the client for a timeline extension to allow the team to recover and deliver quality work

C.

Bring in additional contractors to supplement the team and maintain the delivery timeline

D.

Implement stricter quality controls and code review processes to address the increasing defects

How to approach this question

Look for approaches that balance business value delivery with team sustainability by focusing on core client needs within capacity constraints.

Full Answer

A.Assess the team's current sustainable capacity and work with the client to identify the core features that deliver maximum business value✓ Correct
Executing projects with urgency requires balancing speed with team sustainability, focusing on delivering maximum business value within the team's sustainable capacity constraints.

Common mistakes

Students often choose resource addition or timeline extension approaches rather than recognizing the need to focus on core value within sustainable capacity.

Practice the full PMI PMP Practice Exam 4

90 questions · hints · full answers · grading

More questions from this exam