Hard1 markMultiple Choice
Task 13: Determine appropriate project methodology/methods and practicesmethodology selectionhybrid approachstable requirementsiterative delivery

PMP · Question 63 · Task 13: Determine appropriate project methodology/methods and practices

A project manager is assigned to lead a new mobile application development project. The business requirements are well-defined and stable, but the organization wants to incorporate user feedback throughout development and deliver working features every 4 weeks. The development team has experience with both waterfall and agile approaches. The application must comply with strict data privacy regulations before final release. What methodology should the project manager recommend?

Answer options:

A.

Pure Agile methodology to support iterative delivery and continuous user feedback

B.

Waterfall methodology since requirements are stable and well-defined

C.

Hybrid methodology combining predictive planning with iterative delivery and continuous feedback loops

D.

Iterative methodology with multiple development cycles and user validation points

How to approach this question

Analyze project characteristics including requirement stability, delivery preferences, feedback needs, and regulatory constraints to select the optimal methodology.

Full Answer

C.Hybrid methodology combining predictive planning with iterative delivery and continuous feedback loops✓ Correct
Methodology selection requires analyzing multiple project characteristics including requirement stability, delivery preferences, feedback needs, and regulatory constraints to choose the optimal approach.

Common mistakes

Students often choose pure methodologies rather than recognizing when hybrid approaches better address multiple project characteristics and constraints.

Practice the full PMI PMP Practice Exam 4