    PracticePMI PMP®PMI PMP Practice Exam 4Question 45
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder collaborationdigital transformationshared visionalignment

    PMP · Question 45 · Task 9: Collaborate with stakeholders

    A project manager is working on a digital transformation project involving multiple business units with different priorities and success metrics. The marketing team wants advanced analytics capabilities, the sales team prioritizes mobile accessibility, the finance team focuses on cost control, and the IT team emphasizes security and maintainability. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate stakeholder workshops to identify shared objectives and create a unified vision for the transformation

    B.

    Prioritize requirements based on business impact and resource constraints

    C.

    Create separate project tracks for each business unit to address their specific needs

    D.

    Escalate to senior leadership to define the project priorities and success metrics

    How to approach this question

    Look for collaborative approaches that build shared understanding and unified vision among diverse stakeholders before making decisions.

    Full Answer

    A.Facilitate stakeholder workshops to identify shared objectives and create a unified vision for the transformation✓ Correct
    Effective stakeholder collaboration requires building shared understanding and unified vision among diverse groups with different priorities before making decisions about project direction.

    Common mistakes

    Students often choose prioritization or separation approaches rather than recognizing the need to build stakeholder alignment first.
    Question 44All questionsQuestion 46

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →