    Hard1 markMultiple Choice
    Task 3: Support team performanceperformance supportrole transitioncoachingleadership development

    PMP · Question 38 · Task 3: Support team performance

    A project manager notices that a high-performing team member has started missing deadlines and producing lower-quality work over the past month. The team member was recently promoted to a technical lead role and is now responsible for mentoring junior developers in addition to their individual contributions. Which TWO actions should the project manager take to support this team member's performance?

    Answer options:

    A.

    Reduce the team member's individual workload to focus solely on leadership responsibilities

    B.

    Document the performance decline and establish a formal improvement plan

    C.

    Provide coaching on time management and prioritization skills for balancing individual and leadership responsibilities

    D.

    Have a private conversation to understand the challenges they're facing in their new role

    E.

    Assign a senior mentor to take over the junior developer mentoring responsibilities

    F.

    Extend deadlines for all of the team member's deliverables

    How to approach this question

    Select TWO approaches that provide understanding and support for role transition challenges while developing necessary skills.

    Full Answer

    Supporting team performance during role transitions requires understanding specific challenges and providing targeted coaching to develop the skills needed for expanded responsibilities.

    Common mistakes

    Students often choose workload reduction or formal processes rather than recognizing the need for understanding and skill development support.
    Question 37All questionsQuestion 39

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →