For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 4Question 24
    Hard1 markMultiple Choice
    Task 10: Manage project changeschange managementsupplier issuesimpact assessmentgovernance

    PMP · Question 24 · Task 10: Manage project changes

    During the execution of a predictive project, a major supplier announces they are discontinuing a key component that represents 15% of the project deliverable. Alternative suppliers exist but would require significant design changes and a 6-week delay. The current project timeline has only 2 weeks of buffer remaining. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately implement the design changes and inform stakeholders of the 6-week delay

    B.

    Assess the impact of various response options and prepare a change request with recommendations for stakeholder decision

    C.

    Negotiate with the supplier to continue providing the component until project completion

    D.

    Remove the affected component from the project scope to avoid delays

    How to approach this question

    Look for change management approaches that analyze options and provide stakeholders with information for informed decision-making.

    Full Answer

    B.Assess the impact of various response options and prepare a change request with recommendations for stakeholder decision✓ Correct
    Effective change management requires analyzing response options, assessing impacts, and providing stakeholders with recommendations through proper governance processes.

    Common mistakes

    Students often choose immediate action approaches rather than recognizing the need to follow change management processes and provide stakeholder options.
    Question 23All questionsQuestion 25

    Practice the full PMI PMP Practice Exam 4

    90 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project with a distributed team across...HardQ03During a performance review cycle, a project manager notices that one team member consistently de...HardQ04A cross-functional agile team has been working together for six months and has developed strong t...HardQ05A project team is transitioning from a predictive to an agile approach mid-project due to changin...Hard
    View all 90 questions →