PMP · Question 79 · Task 9: Integrate project planning activities
A project manager discovers that two different teams working on related project components have made conflicting technical decisions that will prevent proper system integration. Each team believes their approach is correct and has valid technical justifications. The integration is scheduled to begin in three weeks. What should the project manager do FIRST?
A project manager discovers that two different teams working on related project components have made conflicting technical decisions that will prevent proper system integration. Each team believes their approach is correct and has valid technical justifications. The integration is scheduled to begin in three weeks. What should the project manager do FIRST?
Answer options:
Bring both teams together to understand the technical approaches and identify integration requirements
Choose the approach from the more experienced team
Escalate the technical conflict to senior management for resolution
Delay the integration timeline to allow more time for resolution
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 2
100 questions · hints · full answers · grading
Expert