    PracticePMI PMP®PMI PMP Practice Exam 2Question 70
    Hard1 markMultiple Choice
    Task 7: Plan and manage quality of products/deliverablestechnical-debtagile-developmentarchitectural-planningsustainable-development

    PMP · Question 70 · Task 7: Plan and manage quality of products/deliverables

    A project team is using Scrum and has been consistently delivering working software each sprint. However, the product owner reports that while individual features work correctly, the overall product architecture is becoming fragmented and technical debt is accumulating. What should the project manager recommend?

    Answer options:

    A.

    Continue with current practices since the team is delivering working software as required

    B.

    Dedicate entire sprints to technical debt reduction and architecture improvement

    C.

    Incorporate architectural planning and technical debt management into regular sprint activities

    D.

    Switch to a different agile framework that emphasizes architecture planning

    How to approach this question

    When technical debt accumulates in agile development, integrate architectural planning and debt management into regular sprint work rather than stopping feature delivery.

    Full Answer

    C.Incorporate architectural planning and technical debt management into regular sprint activities✓ Correct
    Sustainable agile development requires balancing feature delivery with technical health. Incorporating architectural planning and debt management into regular sprints maintains both business value delivery and technical sustainability.

    Common mistakes

    Ignoring technical debt accumulation, stopping feature delivery entirely, or changing frameworks instead of improving practices.
    Question 69All questionsQuestion 71

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →