    PracticePMI PMP®PMI PMP Practice Exam 2Question 65
    Hard1 markMultiple Choice
    Task 1: Execute project with the urgency required to deliver business valuescrum-ceremoniesdaily-standupmeeting-effectivenessteam-coaching

    PMP · Question 65 · Task 1: Execute project with the urgency required to deliver business value

    A project manager is leading a software development project using Scrum methodology. The development team reports that they are spending too much time in the daily stand-up meetings because team members are providing detailed technical explanations rather than brief status updates. The meetings are running 45 minutes instead of the recommended 15 minutes. What should the project manager do?

    Answer options:

    A.

    Eliminate the daily stand-up meetings to give the team more development time

    B.

    Reduce the frequency of stand-up meetings to every other day

    C.

    Coach the team on effective stand-up practices and establish time-boxed formats

    D.

    Assign a different person to facilitate each stand-up meeting

    How to approach this question

    When Scrum ceremonies are ineffective, coach the team on proper practices rather than eliminating or modifying the ceremonies.

    Full Answer

    C.Coach the team on effective stand-up practices and establish time-boxed formats✓ Correct
    Daily stand-ups provide important coordination value in Scrum. When they're ineffective, coaching the team on proper practices (brief status updates, time-boxing) maintains the benefits while improving efficiency.

    Common mistakes

    Eliminating valuable ceremonies, changing Scrum framework elements, or making structural changes without addressing the root cause of ineffective practices.
    Question 64All questionsQuestion 66

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard