Hard1 markMultiple Choice
Task 3: Assess and manage riskstechnical-debtimpact-assessmentintegration-risksunexpected-discoveries

PMP · Question 61 · Task 3: Assess and manage risks

A project manager is working on a complex integration project involving multiple legacy systems. The technical team reports that they have discovered significant technical debt in one of the legacy systems that will require additional work to address before integration can proceed safely. This was not anticipated in the original planning. What should the project manager do FIRST?

Answer options:

A.

Assess the impact of the technical debt on project scope, schedule, and risk profile

B.

Proceed with integration and address technical debt issues as they arise

C.

Immediately begin work to resolve the technical debt

D.

Escalate the technical debt discovery to senior management

How to approach this question

When unexpected technical issues are discovered, assess the full impact first to enable informed decision-making about response options.

Full Answer

A.Assess the impact of the technical debt on project scope, schedule, and risk profile✓ Correct
Unexpected technical discoveries require thorough impact assessment to understand implications for scope, schedule, cost, and risk. This information enables informed stakeholder decision-making about response approaches.

Common mistakes

Proceeding without addressing known risks, starting remediation work without approval, or escalating without providing complete impact information.

Practice the full PMI PMP Practice Exam 2

100 questions · hints · full answers · grading

More questions from this exam