For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 2Question 56
    Hard1 markShort Answer
    Task 6: Plan and manage schedulepert-estimationthree-point-estimationschedule-calculationexpected-duration

    PMP · Question 56 · Task 6: Plan and manage schedule

    A project has the following three-point estimates for a critical activity:<br/><br/>Optimistic (O): 8 days<br/>Most Likely (M): 12 days<br/>Pessimistic (P): 22 days<br/><br/>Using the PERT formula, what is the expected duration for this activity? (Round to one decimal place, enter numbers only)

    How to approach this question

    Use the PERT formula: Expected Duration = (O + 4M + P) / 6. Calculate: (8 + 4(12) + 22) / 6 = (8 + 48 + 22) / 6 = 78 / 6 = 13.0 days.

    Full Answer

    PERT three-point estimation uses the formula (O + 4M + P) / 6 to calculate expected duration. This weights the most likely estimate more heavily: (8 + 4×12 + 22) / 6 = 78 / 6 = 13.0 days.

    Common mistakes

    Using simple average instead of PERT formula, calculation errors, or incorrect formula application.
    Question 55All questionsQuestion 57

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →