    PracticePMI PMP®PMI PMP Practice Exam 2Question 28
    Hard1 markMultiple Choice
    Task 16: Ensure knowledge transfer for project continuityknowledge-transferproject-closurelessons-learnedretrospectives

    PMP · Question 28 · Task 16: Ensure knowledge transfer for project continuity

    A project is nearing completion, and the project manager is preparing for project closure. The team has learned valuable lessons about integration challenges that could benefit future projects. However, team members are already being assigned to new projects and have limited time for closure activities. What should the project manager prioritize for knowledge transfer?

    Answer options:

    A.

    Complete all planned closure documentation before team members are reassigned

    B.

    Schedule individual interviews with each team member to capture their insights

    C.

    Facilitate a focused retrospective session to capture key lessons and integration insights

    D.

    Delegate knowledge capture to team leads who will remain with the organization longer

    How to approach this question

    When time is limited, focus on the most efficient methods that capture the highest-value knowledge while team members are still engaged and available.

    Full Answer

    C.Facilitate a focused retrospective session to capture key lessons and integration insights✓ Correct
    Focused retrospectives efficiently capture key lessons while leveraging team collaboration and shared insights. This approach maximizes knowledge transfer value within time constraints.

    Common mistakes

    Trying to complete all documentation, using time-intensive individual methods, or delegating without ensuring comprehensive knowledge capture.
    Question 27All questionsQuestion 29

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →