    PracticePMI PMP®PMI PMP Practice Exam 2Question 08
    Hard1 markMultiple Choice
    Task 1: Plan and manage project compliancecompliance-managementregulatory-requirementsdata-securityrisk-containment

    PMP · Question 08 · Task 1: Plan and manage project compliance

    A pharmaceutical company project must comply with FDA regulations for clinical trial data management. During a routine audit preparation, the project manager discovers that a team member unknowingly used a non-compliant cloud storage method for storing patient data for the past three weeks. The data includes personally identifiable information and clinical trial results. What should the project manager do FIRST?

    Answer options:

    A.

    Document the issue in the risk register and schedule a compliance review meeting

    B.

    Immediately halt the affected work and assess the full scope of the compliance impact

    C.

    Report the team member to HR for not following established procedures

    D.

    Update the project management plan to include additional compliance training

    How to approach this question

    In compliance violations, especially with regulated industries and sensitive data, immediate containment and assessment must come before documentation, training, or disciplinary actions.

    Full Answer

    B.Immediately halt the affected work and assess the full scope of the compliance impact✓ Correct
    FDA compliance violations involving patient data require immediate action to contain the violation and assess its full scope. This takes priority over documentation, training, or disciplinary measures.

    Common mistakes

    Prioritizing documentation, training, or disciplinary actions over immediate containment of active compliance violations.
    Question 07All questionsQuestion 09

    Practice the full PMI PMP Practice Exam 2

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint planning meeting in a hybrid project, two senior developers disagree about the te...HardQ02A project manager is assigned to lead a new software development project for a financial services...HardQ03During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ04A construction company is building a hospital with strict regulatory requirements, detailed archi...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 100 questions →