    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 16
    Hard1 markMultiple Choice
    Task 2: Manage communicationsProcessCommunicationsStakeholders

    PMP · Question 16 · Task 2: Manage communications

    A project manager identifies that a key stakeholder is not reading the weekly status reports, leading to repeated questions about information already communicated. What is the BEST way to address this?

    Answer options:

    A.

    Add a 'read receipt' to the emails to track compliance.

    B.

    Ask the stakeholder about their preferred communication format and adjust the strategy.

    C.

    Stop sending the reports and only communicate via meetings.

    D.

    Escalate to the stakeholder's manager that they are ignoring project communications.

    How to approach this question

    Focus on the effectiveness of communication, not just the transmission.

    Full Answer

    B.Ask the stakeholder about their preferred communication format and adjust the strategy.✓ Correct
    The Communications Management Plan should be updated based on stakeholder feedback and effectiveness.

    Common mistakes

    Blaming the stakeholder (A, D) instead of adjusting the method.
    Question 15All questionsQuestion 17

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
    View all 20 questions →