    PracticePMI PMP®PMI PMP Mini Practice Exam 3Question 13
    Hard1 markMultiple Choice
    Task 13: Mentor relevant stakeholdersPeopleMentoringStakeholders

    PMP · Question 13 · Task 13: Mentor relevant stakeholders

    A junior project manager is struggling to manage a complex stakeholder group. The program manager (their mentor) notices the junior PM is agreeing to every stakeholder request to avoid conflict. What is the BEST mentoring approach?

    Answer options:

    A.

    Step in and take over the stakeholder meetings until the project is back on track.

    B.

    Role-play negotiation scenarios with the junior PM and provide feedback on saying 'no' constructively.

    C.

    Send the junior PM to a general communication training course.

    D.

    Advise the junior PM to document all requests and let the Change Control Board reject them.

    How to approach this question

    Select the option that builds the mentee's skills rather than doing the work for them.

    Full Answer

    B.Role-play negotiation scenarios with the junior PM and provide feedback on saying 'no' constructively.✓ Correct
    Mentoring is about transferring knowledge and skills. Role-playing is a powerful technique for soft skills.

    Common mistakes

    Rescuing the mentee (A) instead of teaching them.
    Question 12All questionsQuestion 14

    Practice the full PMI PMP Mini Practice Exam 3

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
    View all 20 questions →