PMP · Question 13 · Task 13: Mentor relevant stakeholders
A junior project manager is struggling to manage a complex stakeholder group. The program manager (their mentor) notices the junior PM is agreeing to every stakeholder request to avoid conflict. What is the BEST mentoring approach?
Answer options:
Step in and take over the stakeholder meetings until the project is back on track.
Role-play negotiation scenarios with the junior PM and provide feedback on saying 'no' constructively.
Send the junior PM to a general communication training course.
Advise the junior PM to document all requests and let the Change Control Board reject them.