CPA · Question 06 · Area I: Information Systems
An auditor is evaluating the design of a disaster recovery plan (DRP). The organization uses a 'differential' backup strategy during the week and a 'full' backup on weekends. If the system crashes on Thursday afternoon, which files are required to restore the system to the most recent state?
Answer options:
The last full backup and the differential backup from Wednesday night.
The last full backup and all daily differential backups from Monday, Tuesday, and Wednesday.
The last full backup and the differential backup from Wednesday night.
Only the differential backup from Wednesday night.
82 questions · hints · full answers · grading